Momentum continues at Glass Bottle as we bring this transformative development to life!
Phase 1
• Snagging has begun, with the first batch of apartments presented to the design team.
• Fit-out of common areas—including corridors, lifts, and stair cores—is progressing steadily.
• Scaffold removal and balcony installations are ongoing in the courtyard and east elevation.
• Courtyard works have commenced, with waterproofing underway ahead of landscaping.
• Apartment fit-outs continue to advance, bringing units closer to completion.
• Lift installations are making significant progress. • Joinery installation has started as part of the ongoing apartment fit-out.
• Unitised façade installation is progressing, now reaching up to level 15.
Phase 1B
• In Block L, the Level 18 roof slab was poured at the end of February, marking a key milestone.
• Lift core overrun and parapet upstands are scheduled for completion this week.
• Doka formwork shroud dismantling is set to begin soon, with an expected duration of approximately one week.
Thank you to all stakeholders for your continued commitment to making this landmark development a reality!